UK and Europe strengthen electricity links against backdrop of Brexit uncertainty

The UK continues to press ahead with plans to significantly increase its Interconnector links with Continental Europe.

Negotiations over the UK’s exit from the European Union, currently scheduled for 29 March, have been turbulent to say the least, with the Prime Minister’s Brexit deal twice rejected by the House of Commons. However, this is having no real impact on energy infrastructure, with new developments strengthening electricity links across the Channel. More information on the impact of Brexit on the energy industry can be found here.

The first electricity link connecting Britain with Belgium became operational on 31 January 2019. The 1GW power link had been under construction since 2016, with funding provided by a joint venture between Britain’s National Grid and Belgian system operator Elia.

The Government wants to see all the current planned projects through to operation, the majority of which will not be completed until after the UK has left the EU. Business Secretary, Greg Clark had indicated he was keen for the UK to remain in the EU’s Internal Energy Market, although the final decision will depend on the conditions of any final withdrawal agreement.

 

No alt text provided for this image

 

Following on from the Belgium link, two more links with France are under construction – ElecLink and IFA2 – with both scheduled to be operational by 2020. A North Sea Link with Norway is also progressing, expected to be fully commissioned in 2021.

As a consequence, over the next three years, Interconnector capacity between the UK and Europe is expected to more than double to over 8GW.

This will provide the British power market with access to greater supplies and improved flexibility in meeting peak demand. Tight surplus power margins triggered sharp spikes in Day-ahead power prices last winter, particularly during the Beast from the East cold snap. The threat of cold, windless days will remain a problem for the UK going forward. The incentive for investment in increased interconnection for the UK is clear.

 

Interconnectors

The UK now operates five interconnector links, including the Nemo Link. Three are with mainland Europe via France, Belgium and the Netherlands, and two are with Ireland. Total capacity across the links is now 5GW, with the completion of Nemo. A further 3.4GW of interconnector capacity is currently under construction.

 

UK links target France and Ireland

In addition to those under construction, a further four additional interconnectors with France are in the pipeline. A new 1.4GW FAB cable to Devon was granted planning approval earlier last year. The 2GW AQUIND Interconnector, planned for Portsmouth, received approval from energy regulator Ofgem in September 2017. Further connections include two 1.4GW projects, the GridLink Interconnector in Kent and the Channel Cable. Both are hoping to be online by 2022.

Developers are also looking to take advantage of high renewable availability in Ireland. Utilising the short distance between Wales and the Republic of Ireland, four interconnectors are planned across the Irish Sea. The GreenConnect, Greenlink and Greenwire North and South developments could add 3.5GW of transmission capacity between Britain and Ireland. Ireland is also planning its own direct link with France, but the Celtic Interconnector is only in the early planning stages.

 

Scandinavian connections

The UK also has early plans to tap into the Scandinavian energy market, hoping to take advantage of high levels of installed renewable capacity as well as hydropower reserves in the region. Two interconnector links are in planning with Norway. These will run to Peterhead in Northeast Scotland and Blyth in northern England – both with a capacity of 1.4GW.

A further 1.4GW Viking Link is in planning that will connect the UK with Denmark. Just last week the UK Government gave final approval of the project, which is scheduled to come online in 2023. Developer National Grid Viking Link Limited (NGVL) has explicitly stressed that the UK’s decision to leave the European Union “does not influence the plans to build and operate Viking Link between the UK and Denmark.”

An ambitious 1,000km IceLink interconnector is also in planning and will connect Scotland with Iceland. However, the €3.5bn project is only at the concept stage and it is expected to be at least ten years until this link could be operational.